If you are the first time to contact 070-178 study torrent, you must have a lot of questions. As for this point, we have 24h online workers. Even if it is weekend, we still have online staff to answer your questions. Do not think that you have bothered our staff. We are warmly welcomed you to raise questions about our 070-178 training material. All of you questions will be answered thoroughly and quickly. Even if you have bought our Microsoft Project 2010, Managing Projects demo questions, you are still available to enjoy our online workers' service. Our company has been attaching great importance to customer service. As you can see, we are very responsible for our customers. Do not hesitate. Our 070-178 exam torrent is waiting for you to buy.
Maybe you are in a bad condition now. It does not matter. Life has many turning points. As long as you can seize the opportunity when it appears, you are bound to change your current situation. You can regard our 070-178 training material as a good attempt. Actually, our 070-178 free torrent has helped many people to find a desirable job. You can also have a successful counter attack with the help of our 070-178 study guide. As old saying goes, who laughs last, laughs best. All in all, we hope that you can embrace a bright future.
Many people are worried about that they cannot understand the difficult knowledge of the 070-178 study guide, so most of them just give up trying. Then you are lucky enough to come across our 070-178 pass4sure vce. All the contents of the TS training pdf are compiled by our leading experts. They have accumulated many experiences about the Microsoft 070-178 exam. At the same time, you will have a great sense of achievement after you have mastered the difficult knowledge. Day by day, you will be filled with motivation. The more confident you are, the more successful you are. We would appreciate if you can choose our 070-178 training material.
Maybe you still cannot totally trust our 070-178 updated study torrent. It does not matter. In order to remove your doubts, we have released the free demo of the 070-178 valid vce for you. If you are interesting about our training material, you can download the free demo of the TS study guide on our website. It takes you no more than ten seconds to download the free demo. The free demo of the 070-178 training material is PDF version. What is more, the free demo only includes part of the contents. Most people are willing to choose our 070-178 study guide after trying. Our practice material is different from the traditional test engine. You will have a better experience on our Microsoft Project 2010, Managing Projects prep material. Come to have a try. Our study guide deserves your purchasing.
| Section | Objectives |
|---|---|
| Topic 1: Executing Projects | - Project execution tracking in Microsoft Project
|
| Topic 2: Initiating Projects | - Defining project scope and objectives
|
| Topic 3: Planning Projects | - Resource planning and allocation
|
| Topic 4: Monitoring and Controlling Projects | - Schedule and performance control
|
| Topic 5: Closing Projects | - Project closure activities
|
1. The project you manage has only part-time resources. The part-time resources work four hours a day from Wednesday through Saturday. You need to create a new calendar and set the calendar as the default for your project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A) Change the Calendar type in the Project Options dialog box.
B) Select the part-time calendar from the Change Working Time window.
C) On the Project tab, Select Change Working Time, and then click Create New Calendar.
D) Select the part-time calendar from the Project Information window.
E) Set the calendar type to part-time for all tasks.
2. You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?
A) Click the Insert Milestone button.
B) Remove the predecessor assignments.
C) Select the Mark Task as Milestone check box.
D) Change Work to zero hours.
3. Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday. John, a team member, asks to take Thursday off from work. He will work on Saturday to adjust this time. You need to ensure that the change in John's working time is reflected in the project schedule. What should you do?
A) Update the resource calendar for John by making Thursday as a non-working day and Saturday as a working day.
B) In the Resource Information window for John, change John's availability by modifying the Available From and Available To dates for Thursday to 0 percent and for Saturday to 100 percent.
C) In the Resource Information window for John, select the inactive option for Thursday and cancel the selection of the inactive option for Saturday.
D) Update the project calendar for John by making Thursday as a non-working day and Saturday as a working day.
4. You manage a project according to the schedule as shown in the exhibit. (Click the Exhibit button.)
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A) Set Task 4 as critical.
B) Create a task dependency from Task 4 to Task 6.
C) Add a 1 day lead to Task 4.
D) Set Task 4 as manually scheduled.
5. You create a custom Timeline view of summary tasks and key milestones. You need to send an image of only the custom Timeline view by e-mail. Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)
A) On the File menu, select Save & Send, and then click Create a PDF/XPS Document.
B) On the Format tab, select Copy Timeline, and then click For email.
C) On the File menu, select Save & Send, and then click Send as Attachment.
D) Copy and paste the Timeline view into the body of the e-mail.
Solutions:
| Question # 1 Answer: C,D | Question # 2 Answer: C | Question # 3 Answer: A | Question # 4 Answer: D | Question # 5 Answer: A,C |