NEW QUESTION 108
Who carries out audits that are independent of the project?

  • A. Project Manager
  • B. Quality assurance
  • C. Project Support
  • D. Project Assurance

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 109
Which is a purpose of a Project Product Description?

  • A. Defines what the project must deliver in order to gain acceptance
  • B. Provides a list of all the products to be delivered by the project
  • C. Records the costs and timescales for delivery of the project's final product
  • D. Shows the dependencies between the project's products to aid planning

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 110
Which is a purpose of the Risk theme?

  • A. Establish mechanisms to control any unacceptable deviations from plan
  • B. Establish mechanisms to manage risks at the corporate or programme level of an organization
  • C. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
  • D. Establish a cost-effective procedure to identify, assess and control uncertainty

Answer: D

 

NEW QUESTION 111
Which is one of the three levels of plan in PRINCE2?

  • A. Benefits Review Plan
  • B. Programme Plan
  • C. Team Plan
  • D. Project Brief

Answer: C

 

NEW QUESTION 112
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.

  • A. define the project benefits to be achieved by each of
  • B. define a coding system to provide a unique identifier for the products within
  • C. summarize the results of the quality activities performed on
  • D. provide a framework to design, develop and maintain

Answer: D

 

NEW QUESTION 113
Which describes a risk event?

  • A. The area of uncertainty in terms of the threat or opportunity
  • B. The derivation or sources of a potential risk to the project
  • C. The sequence of events and actions that will be put in place if a risk occurs
  • D. The achievement of a milestone on the project plan

Answer: A

Explanation:
Reference http://prince2.wiki/Risk

 

NEW QUESTION 114
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

  • A. Project mandate
  • B. Initiation stage plan
  • C. Project brief
  • D. Project initiation documentation

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 115
Which is NOT represented by one of the three primary categories of stakeholder identified
in PRINCE2?

  • A. Those who will create the project's outputs
  • B. Those with a financial interest in the project
  • C. Those who will specify the desired outputs of the project
  • D. Those who will manage the project on a day-to-day basis

Answer: D

 

NEW QUESTION 116
What should be considered when defining the number of management stages in a project?

  • A. When the team managers are available
  • B. When key decisions need to be made
  • C. When project support will be available
  • D. When highlight reports will be submitted

Answer: B

Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-management-and-technical-stages/

 

NEW QUESTION 117
Which is NOT included in the PRINCE2 definition of a project?

  • A. A project is based on an agreed Business Case
  • B. A project's purpose is to deliver one or more business products
  • C. A project is a temporary organization
  • D. A project is part of business as usual'

Answer: D

 

NEW QUESTION 118
Which is a benefit of using PRINCE2?

  • A. Can be tailored by leaving out elements of the method for some projects
  • B. Enables the management of projects as well as of 'business as usual' activities
  • C. Avoids the need to involve corporate or programme management
  • D. Can be applied to any type of project

Answer: D

Explanation:
Section: Volume A

 

NEW QUESTION 119
Which is a purpose of the Risk Register?

  • A. List the responsibilities for achieving an effective risk management procedure
  • B. Act as a central record of information relating to the identified risks for the project
  • C. Describe the risk management techniques and standards to be applied to the project
  • D. Act as a repository for informal issues

Answer: B

 

NEW QUESTION 120
Why is the Initiating a Project process used?

  • A. To fully understand how the project objectives will be achieved before committing significant resources
  • B. To enable corporate or programme management to give authorization to deliver a project
  • C. To produce the required Work Packages
  • D. To decide which project approach is suitable for the project

Answer: A

 

NEW QUESTION 121
Which activity takes place within the Managing a Stage Boundary process?

  • A. Produce Highlight Reports
  • B. Produce an Exception Plan
  • C. Take corrective action within the limits of a stage's tolerance
  • D. Authorize a Stage Plan for the next stage

Answer: B

 

NEW QUESTION 122
Identify the missing words in the following sentence.
A benefit of adopting PRINCE2 is that it can be applied to [ ? ] - and can easily be implemented alongside specialist techniques.

  • A. all types of programmes
  • B. any type of project
  • C. programmes and projects
  • D. business as usual

Answer: B

 

NEW QUESTION 123
How does the 'managing product delivery' process achieve its purpose?

  • A. By escalating issues and risks that cannot be resolved within stage tolerance
  • B. By agreeing requirements for how project work should be undertaken
  • C. By producing highlight reports to enable the project board to oversee the work
  • D. By requiring the project manager to produce and monitor team plans

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 124
Which is a purpose of the 'closing a project' process?

  • A. To establish mechanisms for forecasting project objectives
  • B. To establish mechanisms to judge whether the project is still viable
  • C. To provide the project board with information to judge the success of a stage
  • D. To confirm the project has nothing more to deliver

Answer: D

Explanation:
Reference http://prince2.wiki/Closing_a_Project#Objective

 

NEW QUESTION 125
What is the definition of a project outcome?

  • A. A measurable improvement that is perceived as an advantage by one or more stakeholders
  • B. The result of the change derived from using the project's outputs
  • C. The reason for the project
  • D. The project's specialist products.

Answer: B

 

NEW QUESTION 126
Which is a purpose of the Controlling a Stage process?

  • A. Update a Project Plan to incorporate the actuals from a Stage Plan
  • B. Obtain approvals for products delivered in a Work Package
  • C. Select and implement actions that will resolve deviations from a plan within tolerance
  • D. Produce a Team Plan for the work to be assigned to a Team Manager

Answer: C

Explanation:
Section: Volume A

 

NEW QUESTION 127
Which should be funded by a change budget?

  • A. Change Authority
  • B. Initiation stage
  • C. Handover activities
  • D. Increase in agreed scope

Answer: D

Explanation:
Section: Volume A

 

NEW QUESTION 128
What is an advantage of dividing the project into stages?

  • A. The project brief can be updated towards the end of each stage
  • B. the project board can delegate management of the project to team managers
  • C. Detailed plans can be prepared closer to the time events will take place
  • D. The project can be authorized by the project manager on a stage by stage basis

Answer: C

 

NEW QUESTION 129
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

  • A. Issue Register
  • B. Risk Register
  • C. Follow-on action recommendations
  • D. Off-specifications

Answer: C

 

NEW QUESTION 130
Identify the missing product in the following sentence.
When assessing an issue during the Controlling a Stage process, the [ ? ] provides essential information to evaluate the viability of the project.

  • A. Benefits Review Plan
  • B. Project Initiation Documentation
  • C. Configuration Management Strategy
  • D. Project Brief

Answer: B

 